I-95 HOV lanes close 10 p.m. to 5 a.m. Oct. 19-22 and 26-29 up to Indiantown Road. Egret Landing repaving goes on; Loxahatchee bridge work has begun.
Last checked Oct. 20, 2026. This page is refreshed weekly. Sources: the Town of Jupiter Traffic Watch page, Engineering Construction Projects page, the FDOT District 4 Palm Beach County project list and FDOT’s Palm Beach County traffic report for Oct. 16-23.
Three agencies build and close roads in Jupiter. The Town of Jupiter handles town streets. Palm Beach County handles county roads. The Florida Department of Transportation (FDOT) handles I-95, Indiantown Road (State Road 706), U.S. 1, Alternate A1A (State Road 811) and A1A, and Florida’s Turnpike Enterprise runs the Turnpike.
Who to call
- Town road projects: Town of Jupiter Engineering, 561-741-2281
- Report a pothole, sign or streetlight: JupConnect, or the town’s main line, 561-746-5134
- State roads and interstates, live: FL511, or dial 511
- FDOT District 4 communications: 954-777-4302
- Crash or hazard in the road: 911
This week and next
- I-95 HOV lane, nights: FDOT is closing the HOV lane on northbound and southbound Interstate 95 between Clint Moore Road in Boca Raton and Indiantown Road in Jupiter from 10 p.m. to 5 a.m. Monday, Oct. 19, through Thursday, Oct. 22, and again Monday, Oct. 26, through Thursday, Oct. 29. Crews are replacing overhead signs. The general lanes stay open. Questions: Miguel Zamarripa, 786-423-5013.
- Egret Landing: curb and repaving work continues street by street (details below).
- Alternate A1A bridge over the Loxahatchee River: FDOT began work Oct. 13 on the fender system and navigation lights. All lanes are open, and FDOT lists no boating impact.
Town projects under way
| Project | What is happening | Finish (town estimate) |
|---|---|---|
| Egret Landing neighborhood | Curb, sidewalk and driveway repairs, root removal and repaving, street by street | November 2026 |
| Jupiter Park Drive at Central Boulevard | Longer eastbound right-turn lane, new drainage, curbing, swales and repaving | October 2026 (no completion posted yet) |
| Toney Penna Drive and Bush Road | Eastbound through bypass lane and separate southbound left and right turn lanes | August 2026 (town has not posted a final update) |
Egret Landing, the next two weeks
The Egret Landing project page posts a weekly look-ahead. The town lists:
- Repaving, weeks of Oct. 19 and Oct. 26: Quail Point, Robin Lane, Rookery Place, Sanctuary Point, Sawgrass Point, Scrubjay Drive and Scrubjay Lane; Egret Circle South joins the week of Oct. 26.
- Curb work, week of Oct. 19: Egret Circle South, Woodstock Point, Swan Lane, Swallow Lane, Starling Lane, Spoonbill Lane and Sparrow Point, with curb removal starting on Skylark Point, Seagull Point and Lake Shore Drive.
- Curb work, week of Oct. 26: Skylark Point, Seagull Point, Lake Shore Drive, Starling Lane, Spoonbill Lane and Sparrow Point.
No one may park on a street while it is milled or paved, including visitors, lawn crews, pool services, delivery vans and pet groomers. The town asks residents to use a garage or cover cars and to move them off the street before work reaches their block. Schedules depend on the weather and can change.
Jupiter Park Drive
Work began April 20, the town said in its project announcement, and was set to take about six months. The town’s latest status update says crews are widening the westbound lane and filling the old drainage canal on the south side, with delays expected. As of Oct. 20 the town had not posted a completion date. Single-lane closures with flaggers are in place during roadway work.
State roads
- Alternate A1A over the Loxahatchee River: an $830,000 bridge rehabilitation that began Oct. 13 and runs to spring 2027. FDOT allows single-lane closures for equipment deliveries 7 a.m. to 8 p.m. and 9 p.m. to 6 a.m. weekdays, but its Oct. 16-23 report shows all lanes open. Contact: Kashine Johnson, 561-408-9940.
- Coming in January 2027: FDOT plans a $1.5 million Indiantown Road widening between 67th Road North and Central Boulevard, finishing in spring 2027. No closures are scheduled yet.
Nearby
- U.S. 1, Earman River bridge, North Palm Beach (about eight miles south): southbound traffic is shifted onto the new bridge until spring 2027, and the southbound outside lane between Anchorage Drive and Northlake Boulevard closes at times from 9:30 a.m. to 5 p.m. daily, according to the project page.
- U.S. 1, 59th Street to Northlake Boulevard (Riviera Beach, Lake Park and North Palm Beach): one lane closes in each direction from 8 a.m. to 4:30 p.m. through Saturday, Oct. 24, and 9 p.m. to 7 a.m. through Friday, Oct. 23, according to FDOT’s weekly report. The $13.4 million project runs to late 2027.
Florida’s Turnpike
Florida’s Turnpike Enterprise is running a Project Development and Environment study on widening the Turnpike from Indiantown Road in Jupiter to Okeechobee Road in Fort Pierce, about 37 miles, including new bridges over the Loxahatchee River. It is a study, not construction, and the town’s Turnpike page lists no current closures.
Check before you drive
- Jupiter Traffic Watch: live Waze traffic for town streets.
- FL511: cameras, crashes and lane closures on I-95, the Turnpike and state roads; also by phone at 511.
- FDOT District 4 lane closures: the weekly Palm Beach County traffic report.
- Palm Beach County Engineering: county road projects.
- Private development around town: major building sites that can bring trucks and lane shifts.
What this means for you
- Driving I-95 late at night through Oct. 29? The HOV lane is closed from 10 p.m. to 5 a.m. Monday through Thursday; use the general lanes.
- In Egret Landing, check the weekly street list and keep cars off the street on paving day.
- Expect flaggers at Jupiter Park Drive and Central Boulevard until the town says the project is finished.
Related: getting around Jupiter, building permits and zoning and who to call in town government.
Frequently asked questions
Where can I check Jupiter road closures?
The town’s Traffic Watch page lists town road projects and shows live Waze traffic. For interstates and state roads, use FL511 at fl511.com or dial 511.
Are I-95 lanes closed in Jupiter this week?
FDOT is closing the I-95 HOV lane in both directions between Clint Moore Road in Boca Raton and Indiantown Road in Jupiter from 10 p.m. to 5 a.m. Monday, Oct. 19, through Thursday, Oct. 22, and Monday, Oct. 26, through Thursday, Oct. 29, to replace overhead signs.
What is the construction on Jupiter Park Drive?
The town is extending the eastbound right-turn lane at Central Boulevard, adding drainage, curbing and swales and repaving. Work began April 20 and is scheduled to finish in October 2026, with single-lane closures and flaggers.
When will the Egret Landing road work be finished?
The town lists a November 2026 completion for the roughly 180-day project. Curb and repaving work moves street by street, and cars cannot park on a street while it is milled and paved.
Is Florida’s Turnpike being widened in Jupiter?
Florida’s Turnpike Enterprise is studying widening the Turnpike from Indiantown Road in Jupiter to Okeechobee Road in Fort Pierce, about 37 miles. It is a study; the town lists no current closures.